South Valley WRF Project 5
Construct a new multi-level grit removal building, including grit removal basins, grit pumping facilities, grit washing, conveying equipment and yard piping.
completed
Construct a new multi-level grit removal building, including grit removal basins, grit pumping facilities, grit washing, conveying equipment and yard piping.
New 2MGD WTF for a raw food processing plant, includes a 580-foot x 290-foot concrete Covered Anaerobic Lagoon, Aerobic Basin, Secondary Clarifier, and Headworks, Blower and Biogas Buildings.
Replace the existing single lane, tri-span Williams Creek (Shoup) Bridge with an updated dual lane, single span structure utilizing an arched steel and suspension cable support system.
Raise embankments, and construct a new interior drainage pump station and gatewell capable of discharging 280,000 GPM.
Two new bridges over the St. Joe River and St. Maries River Railroad.
New administrative facility with vehicle storage, maintenance area, and residential units.
The 42,400 SF Red Flag 5th Generation Addition provides operational training facilities to support large scale air combat exercises.
Construct Solids Handling and expand the Administration buildings, demolish and replace the entire mechanical and electrical systems.
Repair existing target emplacements on two adjacent military training ranges…
Upgrade the existing wastewater treatment plant while maintaining complete plant operations.